Bids have been invited by the central electricity supply of Odhisa for the power distribution project in various towns of Odhisa, under R-APDRP.
The work related to the bids would come in four packages for engineering, supply, erection and commissioning of new 33 & 11 KV lines, DTs, VCB, underground cabling, upgradation / augmentation of distribution transformers, HT/LT line, AB cabling, static meters for consumers, service connection boxes and automated sectionalisers, RMU & FPI as given below:
Package-I for Bhubaneswar, estimated to cost Rs 111.18 crore. Work on the project is expected to be completed in 18 months
Package-II for Cuttack, estimated to cost Rs 74.41 crore ,which is scheduled for completion in 18 months
Package-III for Khurda, Jatni, Puri, Dhenkanal, Angul, Talcher, Jagatsingpur, Kendrapara, Pattamundei and Paradeep towns, estimated to cost Rs 66.17 crore, which is expected to be completed in 12 months.
Package-IV for Bhubaneswar and Cuttack towns, estimated to cost Rs 12.2 crore and expected to be completed in six months