The Energy Bhawan is being constructed at Bemina by the Jammu and Kashmir Energy Development Agency (JKDEA) is expected to completed in December 2014.
The Energy Bhawan would be three storied building which will have the office of Directorate of JKEDA, State Council for Science and Technology, District Office JKEDA besides a conference hall. The total cost for the project is estimated at the cost of Rs 4.49 crores out of which an amount of Rs 2.12 crore has been incurred till end June this year.
The construction work was begun in June last year and is likely to be completed by December 2014 as the construction work in full swing while as 60 per cent physical progress has been achieved so far .